Land (Owned) | - |
Civil works and Buildings (50000 sq. ft. @ 1000/-) | 500.00 |
Plant and machinery (Annexure) | 2567.50 |
Misc. Fixed Assets | 521.10 |
DG set | 4.40 |
Escalation & Contingencies | 179.65 |
Preliminary & Preoperative Expenses | 68.37 |
Sub-total (A) | 3841.02 |
Total Working Capital Required (25% of 1st Year Project Turnover) (B) | 50.00 |
Total Project Cost | 3891.02 |
Amount | |
Term Loan (A) | 2304.61 |
Working Capital (B) | 30.00 |
Total (A+B) | 2334.61 |
Equity | 1556.41 |
Total Funds Required | 3891.02 |
Year |
Year |
Year |
Year |
Year |
|
---|---|---|---|---|---|
Target Revenue | 2342.40 | 2342.40 | 2342.40 | 2342.40 | 2342.40 |
Break Even Point | 71.65% | 63.99% | 57.12% | 51.32% | 46.26% |
DSCR including Principal Repayment | 2.72 | 2.14 | 2.42 | 2.72 | 3.08 |
Power Rate Per Unit | 8.5 Rs./ Unit |
Power Requirement | 20 Kwh Per Year |
Interest Rate Assumed | 8.50% |
Repayment period | 9 Months Moratorium and 7 Years' Repayment |
Water Requirements | 50000 Liters |
Training Institutes | India Institute of Entrepreneurship |
Whether the service is in the Negative list under NEIDS and MSME? | No |