Proposed Project College
capacity Capacity of the Plant/Unit (at 100% capacity utilization)

3000 students/annum


Year wise capacity utilization

image

Year

80%

image

Year

85%

image

Year

90%

image

Year

95%

image

Year

100%


Final Product

alu

Education

Infrastructure and Equipments Required

image Land
image Building
image Computer

Employment Generation

  • 1 Principal
  • 70 Professors
  • 3 Manager/Dean
  • 10 Lab Assistant
  • 3 Library in-charge
  • 10 Office Staff/ Administrator
  • 15 Sweeper
  • 10 Security Guard
Owned Land -
Civil works and Buildings (99700 sq. ft.) 1,364.88
Fixed Assets 483.49
Misc. Fixed Assets 100.00
DG set 400 KV 4.40
Water Motor 5.00
Escalation & Contingencies 97.64
Preliminary & Preoperative Expenses 124.46
Sub-total (A) 2179.87
Working Capital Margin 181.00
Total Project Cost 2360.87
Total Working Capital Required (B) 452.50
Amount
Term Loan (60% of A) 2632.37
Term Loan -
Working Capital Loan 271.50
Total 1664.41
Equity 967.96
Total 2632.37

Financial Benchmarks

image

Year

image

Year

image

Year

image

Year

image

Year

Target Revenue 216.09 268.15 356.49 450.57 532.32
Break Even Point 78% 75% 69% 65% 62%
DSCR including Principal Repayment 3.14 2.50 2.81 3.19 3.68

Power Rate Per Unit 8.5 Rs./unit
Power Requirement 425882.3 kwh per year
Interest Rate Assumed 9.50%
Repayment Period 12 months Moratorium and 7 years repayment
Training Institutes NA
Whether the service is in the Negative list under NEIDS and MSME? No